News from City Hall

ENGINEERING

CITYWIDE PAVING UPDATE

Earlier this year in April, Tucker Mayor and Council approved a contract with ER Snell to repave streets. The streets were prioritized from the latest Pavement Management Study based on the Pavement Condition Index scores. Tucker staff secured a Georgia DOT LMIG funding grant to resurface Henderson Road while the remaining roads will be funded by the SPLOST II tax approved by voters for a total of $2,859,726.75 plus contingency.

AS OF LAST MONTH 15 ROADS HAVE BEEN COMPLETED:

  • Brookes Walk • Tucker North Court • Tucker North Drive • Stella Burns Drive • Angie Drive • Winding Way • Wender Drive • Windview Court • Windy Court • Winding Woods Drive • Henderson Summit • Cold Water Canyon Drive • Bailey Road • Railroad Ave (West) • Bancroft Circle • Montreal Industrial Way

IN PROGRESS:

  • Henderson Road • Oakwood Drive • Comanche Drive • Winbrooke Lane • Terri Lynn Court

TO BE COMPLETED:

  • Velma Burns Drive • Lilburn Stone Mountain Road • Silver Hill Court

PARKS AND RECREATION

TUCKER TOWN GREEN IS ON SCHEDULE FOR COMPLETION

Construction continues to move forward and now upward as foundations have been laid and filled. Last month, the Mayor and Council approved a contract for commissioned sculpture art for the northwest corner of the green. The selection committee was made up of various stakeholders and local artists, and all were very excited to offer the award to Phil Proctor of Nucleus Sculpture Studio, LLC. The commissioned piece will use steel to create an artistic representation of the standard TKR that reflects Tucker’s industrial past and its sense of community.